Construction progress

lamp lamp lamp

Construction status:Arrangement of vertical elements of the 10th floor, brickwork at level 5 level. Installation of windows on the 1st floor, facade 1-2 floor. Arrangement of stairs of basement and 1 floor.

Expected time of construction: 2Q 2018

status status
10

floors

completed

Works against 0,000 - 100%
Frame -41.25%
Brickwork - 15.83%
Interior fittings - 0%

Windows - 0%
Facade - 2.92%

Inside - 0%
Outsid - 0%

We regularly inform you about the stages of work by posting photo reports.

see the progress webcam
Construction activities
26 September 2017
Arrangement of vertical elements of the 10th floor, brickwork at level 5 level. Installation of windows on the 1st floor, facade 1-2 floor. Arrangement of stairs of basement and 1 floor.
eye
Construction activities
08 September 2017
Arrangement of vertical elements of the 10th floor, brickwork at the 4th floor, installation of windows on the 2nd floor level.
eye
Construction activities
29 August 2017
Arrangement of vertical elements of the 8th floor, brickwork at the 3rd floor level. Installation of windows on 1-2 floors.
eye
Construction activities
11 August 2017
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
eye
Construction activities
28 july 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
18 july 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
30 june 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
9 june 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
30 may 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
10 may 2017
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
eye
Construction activities
27 february 2017
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
Construction activities
14 february 2017
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
Construction activities
31 january 2017
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
Construction activities
5 january 2017
A pile field is being made and vertical structures of the ground floor are being reinforced
eye
Construction activities
4 november 2016
Commencement of pile field works and reinforcement of the basement vertical components
eye
Construction activities
18 September 2017
Construction of the floor slab floor 10, brickwork at the level of 4-5 floors. Facade construction.
eye
Construction activities
04 September 2017
Arrangement of vertical elements at the level of 8 floors, brickwork at the level of 3 floors. Installation of windows on floors 1-2 and facade works on 2 level.
eye
Construction activities
22 August 2017
Arrangement of vertical elements of the 8th floor, brickwork at the 3rd floor level. Installation of windows on 1-2 floors.
eye
Construction activities
7 August 2017
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
eye
Construction activities
24 july 2017
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
eye
Construction activities
10 july 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
23 june 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
19 june 2017
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
Construction activities
19 may 2017
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
eye
Construction activities
7 march 2017
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
Construction activities
20 february 2017
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
Construction activities
7 february 2017
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
Construction activities
23 january 2017
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
Construction activities
15 december 2016
A pile field is being made and vertical structures of the ground floor are being reinforced
eye

Feedback

Name:* E-mail:* Telephone:* Message text:*