Construction activities
Arrangement of vertical elements of the 10th floor, brickwork at level 5 level. Installation of windows on the 1st floor, facade 1-2 floor. Arrangement of stairs of basement and 1 floor.
Arrangement of vertical elements of the 10th floor, brickwork at the 4th floor, installation of windows on the 2nd floor level.
Arrangement of vertical elements of the 8th floor, brickwork at the 3rd floor level. Installation of windows on 1-2 floors.
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
A monolithic frame is being installed and the second level of the car park is being concreted.
A monolithic frame is being installed and the second level of the car park is being concreted.
A monolithic frame is being installed and the second level of the car park is being concreted.
A monolithic frame is being installed and the second level of the car park is being concreted.
Commencement of pile field works and reinforcement of the basement vertical components
Construction of the floor slab floor 10, brickwork at the level of 4-5 floors. Facade construction.
Arrangement of vertical elements at the level of 8 floors, brickwork at the level of 3 floors. Installation of windows on floors 1-2 and facade works on 2 level.
Arrangement of vertical elements of the 8th floor, brickwork at the 3rd floor level. Installation of windows on 1-2 floors.
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
A monolithic frame is being installed and the second level of the car park is being concreted.
A monolithic frame is being installed and the second level of the car park is being concreted.
A monolithic frame is being installed and the second level of the car park is being concreted.
A monolithic frame is being installed and the second level of the car park is being concreted.
A pile field is being made and vertical structures of the ground floor are being reinforced