Construction progress

lamp lamp lamp

Construction status:Work on the improvement of the adjacent territory has been renewed. Work on the lighting of the facades continues. Monolithic works had been finished on the 19th floor and have started on the 20th floor started. Brickwork on 5-9th floors has been finished; the work on 10-15th floors is continuing. Facades: installation of SPOK (windows). Installation of a clinker facade on a 10-storey section of the building. Installation of a heater under the facade of ceramic granite on the side of Zhilyanskaya street.

Expected time of construction: 3Q 2018

status status
17

floors

completed

Works against 0,000 - 100%
Frame -36.04%
Brickwork - 9.79%
Interior fittings - 0%

Windows - 0%
Facade - 2.5%

Inside - 0%
Outsid - 0%

We regularly inform you about the stages of work by posting photo reports.

see the progress webcam
28 March 2018 year
eye
07 March 2018 year
eye
19 February 2018 year
eye
24 January 2018 year
eye
30 November 2017 year
eye
21 November 2017 year
eye
02 November 2017 year
eye
26 September 2017 year
Arrangement of vertical elements of the 10th floor, brickwork at level 5 level. Installation of windows on the 1st floor, facade 1-2 floor. Arrangement of stairs of basement and 1 floor.
eye
08 September 2017 year
Arrangement of vertical elements of the 10th floor, brickwork at the 4th floor, installation of windows on the 2nd floor level.
eye
29 August 2017 year
Arrangement of vertical elements of the 8th floor, brickwork at the 3rd floor level. Installation of windows on 1-2 floors.
eye
11 August 2017 year
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
eye
28 July 2017 year
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
18 July 2017 year
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
30 June 2017 year
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
09 June 2017 year
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
30 May 2017 year
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
11 May 2017 year
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
eye
27 February 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
14 February 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
31 January 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
05 January 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
04 November 2016 year
Commencement of pile field works and reinforcement of the basement vertical components
eye
10 April 2018 year
eye
19 March 2018 year
eye
27 February 2018 year
eye
08 February 2018 year
eye
24 November 2017 year
eye
10 November 2017 year
eye
25 October 2017 year
eye
18 September 2017 year
Construction of the floor slab floor 10, brickwork at the level of 4-5 floors. Facade construction.
eye
04 September 2017 year
Arrangement of vertical elements at the level of 8 floors, brickwork at the level of 3 floors. Installation of windows on floors 1-2 and facade works on 2 level.
eye
22 August 2017 year
Arrangement of vertical elements of the 8th floor, brickwork at the 3rd floor level. Installation of windows on 1-2 floors.
eye
07 August 2017 year
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
eye
24 July 2017 year
Arrangement of vertical elements of the 6th floor, brickwork at the 3rd floor level.
eye
10 July 2017 year
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
23 June 2017 year
A floor slab and vertical elements are being installed on the 4th floor. A floor slab on the 5th floor is about be installed. The elevator shaft on the 4th floor is about to be completed.
eye
19 June 2017 year
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
eye
19 May 2017 year
A floor slab is being installed between the 2nd and 3rd floors. Vertical elements of the third floor are being installed. The elevator shaft on the 3rd floor is being fitted.
eye
07 March 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
20 February 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
07 February 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
21 January 2017 year
A monolithic frame is being installed and the second level of the car park is being concreted.
eye
15 December 2016 year
A pile field is being made and vertical structures of the ground floor are being reinforced